Platform Houchin, Santa Barbara Channel

This article provides information on the history of OCS Lease P-0166 and updates the decommissioning status of California OCS Platforms Hogan and Houchin which are in federal waters offshore Santa Barbara County, California. Listed below are key events in the history of the OCS Lease P-0166. More details are provided in the attachment which was prepared by John Smith who before retiring from BOEM in 2017 was actively involved in the long-running supplemental bond dispute between MMS/BOEM and Signal Hill Services, Inc., which began shortly after MMS approved the assignment of OCS Lease (P-0166) held by Phillps Petroleum Corporation (now ConocoPhillips Corp.) and two other companies to Signal Hill Services Inc. (Signal) in 1991.

Year/MonthLease Activity
1967U.S. Bureau of Land Management grants OCS Lease P-0166 to Phillips Petroleum   Corp., Continental Oil Company, and Cities Service Company.
1967 – 1968Hogan and Houchin platforms are installed.
1967 – 2010 75 wells were drilled from the platforms, the majority in 1967-1968 and 1970s. 
February 1991MMS approves assignment of the lease to Signal.
September 2019Production is terminated at platforms.
October 2020Signal relinquishes the lease to BOEM.
November 2020BSEE orders ConocoPhillips Corp. (COP) and other predecessor lessees to decommission the Hogan and Houchin platforms.
January 2021COP and other predecessor lessees file an appeal with IBLA contesting BSEE/BOEM determination they held decommissioning obligations.
February 2021IBLA grants approval of Partial Stay Agreement between BSEE/BOEM and appellants to maintain and monitor the platforms. 
November 2024Signal files for bankruptcy under Chapter 7 of the U.S. Bankruptcy Code.
2021 – 2026Monitoring, maintenance and major refurbishment of the platforms are ongoing to support safety of offshore personnel involved in well plugging and abandonment operations.

Since OCS lease P-0166 was relinquished in 2020, removal of Hogan/Houchin platforms has been stalled by a prolonged dispute over decommissioning obligations between BSEE/BOEM and predecessor OCS lessees (ConocoPhillips Corp., OXY USA Inc., Devon Energy Resources Inc.). The IBLA case has now been ongoing for more than 5 years and has the potential to set a precedent based on the arguments of the appellants who assert: 

  1. They had no accrued decommissioning obligations at the time of the 1991 assignment of the lease because pursuant to their 1961 OCS lease agreement decommissioning obligations did not accrue until the lease was relinquished, which occurred in 2020 when Signal quitclaimed the lease to BOEM. 
  2. The OCS rules changes promulgated in 1997, which stated a lessee’s decommissioning obligation “accrues to the lessee when a well is drilled, the platform or other facility is installed, or the obstruction is created.” (30 CFR   250.110), cannot be applied retroactively.
  3. The 1961 OCS lease did not include a term by which the lessee agrees to be bound by “future” OCS regulations, which later became a standard provision in OCS lease agreements.  

The IBLA case is very concerning because there is currently no financial security available to cover the costs of decommissioning the Hogan and Houchin platforms which were very conservatively estimated by BSEE to total $85 million in 2020. If the IBLA or judicial courts eventually rule COP and former lease owners did not accrue decommissioning obligations, either in whole or in part, the federal government and American taxpayers will be responsible for covering the unfunded decommissioning obligations.

Read Full Post »

Platform Houchin, Lease OCS-P 0166, Santa Barbara Channel

In light of the decommissioning fire at Platform Habitat, I checked on the status of well plugging operations at Platforms Hogan and Houchin.

BSEE (2020) estimates the cost of decommissioning these facilities to be $85 million (too low), and there is no collateral or third party guarantee.

The responsibility for decommissioning these platforms has yet to be settled. ConocoPhillips, Oxy, and Devon have appealed decommissioning orders from BSEE. The Interior Board of Land Appeals (IBLA) has yet to rule on those appeals. The appellants are funding some plugging operations and facility upgrades pending the IBLA decision.

Per BSEE’s borehole file, this is the current status of the Hogan and Houchin wells:

  • 33 completed and not yet plugged; these wells were drilled between 1968 and 2010
  • 43 temporarily abandoned (TA) wells plugged in accordance with 30 CFR § 250.1721
  • 10 wells have been updated to TA status in the past 6 months (latest 3/22/2026), so some progress is being made
  • 0 permanently abandoned wells (30 CFR § 250.1715)

Therefore, by my count, 33 wells have yet to be TA’d, and all 76 wells remain to be PA’d. Note that the lease was relinquished nearly 6 years ago (10/14/2020).

If you are interested in the Hogan/Houchin mess or decommissioning liability in general, I highly recommend that you look at Devon’s informative and rather compelling appeal to IBLA. Similar appeals were submitted by Oxy and ConocoPhillips.

Lease history (excerpted from the Devon appeal):

  • Lease OCS-P 0166 was issued effective January 1, 1967.
  • Phillips Petroleum Company (“Phillips”) (predecessor to ConocoPhillips), Cities Service Oil Company (predecessor to Oxy), and Continental Oil Company (predecessor to ConocoPhillips) were the initial lessees
  • Phillips was designated operator on January 25, 1967
  • February 28, 1983: Petro-Lewis Funds, Inc., obtained the 37.5% interest of the Continental Oil Company (which in 1979 had changed its name to Conoco Inc., now Conoco Phillips Company (“ConocoPhilips”)).
  • November 1983: Cities Service Oil Company assigned its 37.5% interest to Cities Service Oil and Gas Corporation (now OXY U.S.A. Inc).
  • July 2, 1987: the Minerals Management Service (“MMS”) approved two more assignments of the Lease. One, from PetroLewis Funds, Inc. to American Royalty Producing Company (“American Royalty”), was approved retroactively to December 31, 1984. The other, from American Royalty to Santa Fe Energy Company(“Santa Fe”), was approved retroactively to April 30, 1987.
  • April 1, 1988: Santa Fe transferred a 3.75% interest to Maersk Energy Incorporated, reducing Santa Fe’s share to 33.75%.

1991 Assignment to Signal Hill: MMS approved assignment of the lease to Signal Hill effective February 5, 1991. The assignment was approved without any provision under which the assignors agreed to be liable for decommissioning operations on the lease. MMS’s approval actually had the opposite effect, leaving such obligations to the assignee. The assignment was approved despite concerns within the MMS about the financial strength of Signal Hill and the technical competence of Pacific Operators Offshore Inc (POOI), the affiliate that would operate the facilities.

Comments:

  • The assignment to Signal Hill should have never been approved. The outcome was predictable.
  • The Devon, Oxy, and ConocoPhillips appeals are very strong and would seem to have a good chance of success. Perhaps that is why the IBLA decision is taking so long (nearly 5 years to date).
  • Given the uncertainty regarding this appeal, the absence of transparency about other potential decommissioning liabilities, and the uncertainties regarding the administration of predecessor liability, this is not the time to be relaxing financial assurance requirements and further exposing taxpayers to decommissioning risks.

This is the final day to comment on BOEM’s proposal: