No major new developments were mentioned at today’s Unified Command Briefing (1500 CDT). Summary:
- Still unable to secure the source by actuating BOPE with the ROV. New intervention options are being designed.
- The in situ burn program was scheduled to begin today, but a report is not yet available.
- Subsurface containment and collection system will be ready in 2-4 weeks
- Development Driller III will spud relief well by Friday
- 100,000 feet of boom deployed for coastal protection purposes
- No apparent change in well flow rate.