Shell’s damage assessment of the West Delta 143 (WD 143) platforms revealed significant structural damage. Shell estimates that that the WD-143 “A” platform facilities will be off line for repairs until the end of 2021, and that the facilities on our WD-143 “C” platform will be operational in Q4 2021. Shell expects to resume production from their Olympus platform, which flows across the WD-143 “C” platform, in Q4 2021, and from their Mars and Ursa facilities, which flow across the WD-143 “A” platform, in Q1 2022.
Mars, Olympus, and Ursa account for most of the GoM production that remains shut-in as a result of Hurricane Ida.